White Hart Lane will be formally handed over to our construction partner at 07:00 on Monday 15th May. There will then be a period of between 48-72hrs wherein various services are terminated and decommissioned.

During this period, demolition plant will arrive and assemble and the site will be secured by perimeter hoarding. The demolition itself in principle is phased, with initial focus on the existing North Stand.

However, it is recognised that the exact approach may change according to advice received from the demolition contractor.

It is fair to say that next week will be a very emotional day for all and the club is expecting a large turn-out both in and around the stadium.

A party atmosphere will be encouraged and hosts and club staff will be on hand to help and assist where necessary.

Detailed celebrations are still being finalised however they will extend late into the evening and more precise arrangements will be communicated through usual channels later this week.